Floods inflict $2.29mn losses to 105 mini hydel power stations in KP

PESHAWAR: The August 27 devastating floods have inflicted over $2.29 million losses to 105 mini macro hydel power stations in Khyber Pakthunkhwa.

“The devastations caused by unprecedented floods to energy and power infrastructure was immense and as per our initial damage assessment report, 105 mini macro hydel power stations in nine districts of Malakand and Hazara divisions were either damaged or destroyed,” said Faisal Dawar, Project Director, Mini Macro Hydel Power Stations, Provincial Energy Development Organization (PEDO) while talking to APP.

Nine power stations were damaged in Batagram with an estimated financial losses of Rs 9,825,000, eight in Manshera with Rs 89,800,000 losses, 25 in Swat with Rs 184,000,000 losses and 13 in Shangla with Rs 56,000,000 losses, according to a senior official of the KP Energy Department.

Similarly, floods caused damages to 13 mini macro power stations in Kohistan having estimated financial losses of Rs 75,600,000, 19 in Chitral with Rs 41,140,000 losses, 14 in Dir Upper with 19,646,000 losses and two in Lower Dir with Rs 1,450,000 losses while two in Buner with Rs 3,700,000 losses.

As per initial flood damages reports, the energy department official said that total losses to these power stations were estimated Rs 481,209,000 ($2,209,002.02).

The ruthless flash floods on one-side had affected over 30 million people in the country by destroying their properties, livestock and standing crops, besides damaging mini, macro hydel power stations in nine northern districts of Malakand and Hazara divisions on other side thus causing immense problems for electricity consumers.

Destroying expansive hotels, roads and bridges especially in Kalam, Bahrian Swat and Kohistan, livestock, standing crops and orchards in Nowshera, Charadda and DI Khan, the merciless record-breaking floods in River Swat along with unprecedented high torrential rains during July and August had also damaged infrastructure and power houses of majority of these mini – macro hydel power stations affecting thousands.

The project director said reports of far-flung and remote power stations were awaited especially from Kalam and Upper Kohistan due to destruction of roads and bridges by the flash floods and heavy torrential rains recorded in July and August this year.

According to Met Office, highest rain of 753 milimeters was recorded in Badian in Sindh province followed by 576mm in Kakol Abbottabad and 509mm by Malam Jabba Swat and Balakot Manshera during July 1 to August 31, 2022 which resulted an increasing flow of water in rivers and caused flash floods.

“As result of highest floods, the imported machinery purchased during 2017-18 for these stations were also destroyed and federal government would be approached for allocation of funds to reconstruct these damaged/destroyed power stations on priority basis due to immense economic and power generation potential for benefits of local population,” the project director said.

Faisal Dawar said power houses of these stations in Dubair valley in Lower Kohistan and Kalam, Bahrian in Upper Swat were badly damaged due to highest velocity of the flash floods in these areas.

Besides severe damage to 400 kilowatt (KW) Bahrian power station, 500KW Atror and 15 KW Balgary in Swat, the devastated floods also caused damages to 300KW Ronalia and 40KW Shishal Kiyal power stations in Kohistan and 300KW Bala Ajmir power station in Shangla.

In Manshera, he said that 30KW Kotkay, 100KW Balmunawar and 100KW Kandwara in Kaghan Naran were damaged.

The project director said that a total of 316 mini – macro hydel power stations were completed in June this year out of which 105 were damaged/destroyed by the natural calamity.

He said these power stations were benefitting the local population and about 400 families were provided electricity from Ajmir power station.

However, in the wake of devastated flood, the power supply system of Ajmir was disconnected and most of the families have approached the deputy commissioner for its reconstruction and restoration of power supply on priority basis.

Fiazur Rehman Khan, a resident of Kohistan told APP that these power stations were main source of electricity supply to local population for their domestic needs and its damage deprived many consumers of an inexpensive electricity.

He said its reconstruction and rehabilitation should be prioritized on the pattern of rebuilding financial package for destroyed houses and others structures so that people of these remote areas could be benefitted and forest resources could be saved.

The KP’s electricity demand is generally between 2,500 MW to 2,800 MW and supply is around 1600 MW to 1800MW of which nearly 1,000 MW was being withdrawn from the national power control system.

In order to meet consumers’ demands, about 800MW electricity would be generated from under construction Mohmand dam having storage capacity of 1.2MAF water, official in PESCO informed.

He said around 6,000MW was being obtained from hydel resources having power generation cost of about Rs 63 billion against 50,000 MW potential of Pakistan including 30,000MW in KP.

Besides construction of large dams including Diamir Bhasha, Kurram Tangi and Mohmand dams, he said we need to give focus on construction of small and medium power stations and dams as these were cost and time efficient.

As per international practice, he said priority should be given to small dams and power stations as these require minimum time in construction and installation of power stations besides covering minimum land for storage of water due to their imperative role in agricultural productivity in local areas.

Must Read

Fighting the Kuki-Chin Armed Movement

The Bangladesh government has garnered significant experience in countering insurgency activities in the Chattagram Hill Tracts (CHT). Through operations like "Operation Dabanal," the Bangladesh...

By-elections as expected

Epaper_24-04-24 LHR