ISLAMABAD: Pakistan Nuclear Regulatory Authority (PNRA) granted Operating License (OL) to Karachi Nuclear Power Plant Unit-3 (K-3) on Wednesday upon completion of the licensing process under regulations PAK/909 and demonstration of safe operation of the plant.

The licensing process for OL includes review of licensing submissions, inspections during initial fuel loading, initial criticality, low power and power ascension tests, and operation at full power. K-3 is a Chinese designed (Hualong One) Pressurized Water Reactor (PWR) of 1100MW and it is the second such unit deployed at the Karachi site adding 1100MW to the national grid. Earlier in June 2022, PNRA also granted Operating License to Karachi Nuclear Power Plant Unit-2 (K-2) with an installed capacity of 1100MW.

The site for K-3 was registered in May 2014 and construction license was awarded in November 2015. PNRA issued Fuel Load Permit (FLP) to K-3 in December 2021 following the completion of review and assessment of Final Safety Analysis Report (FSAR) and other relevant documents. After successful completion of criticality and pre-operational tests, K-3 submitted the application for issuance of Operating License in October 2022.

PNRA performs regulatory oversight during all the stages of licensing process and throughout the active lifecycle, which plays a pivotal role in safe operation of nuclear power plants in Pakistan. It is important to highlight that all nuclear power plants in Pakistan are operating under continuous regulatory surveillance of PNRA.

 

 

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Must Read

PM directs committee constitution to consult provinces on carbon credits policy

ISLAMABAD: Prime Minister Shehbaz Sharif has directed to constitute a committee for consultation with the provinces for policy-making on guiding principles for carbon credits. While...